RAYTHEON CO/ | 2013 | FY | 3


Commitments and Contingencies
Leases—At December 31, 2013, we had commitments under long-term leases requiring annual rentals on a net lease basis as follows: 
(In millions)
 
2014
$
205

2015
173

2016
130

2017
102

2018
83

Thereafter
293


 
Rent expense was $248 million, $258 million and $271 million in 2013, 2012 and 2011, respectively. In the normal course of business, we lease equipment, office buildings and other facilities under leases that include standard escalation clauses for adjusting rent payments to reflect changes in price indices, as well as renewal options.
 
At December 31, 2013, we had commitments under agreements to outsource a portion of our information technology function, which have no minimum annual payments.
 
Environmental MattersWe are involved in various stages of investigation and cleanup related to remediation of various environmental sites. Our estimate of the liability of total environmental remediation costs includes the use of a discount rate and takes into account that a portion of these costs is eligible for future recovery through the pricing of our products and services to the U.S. Government. We consider such recovery probable based on government contracting regulations and our long history of receiving reimbursement for such costs, and accordingly have recorded the estimated future recovery of these costs from the U.S. Government within contracts in process, net. Our estimates regarding remediation costs to be incurred were as follows at December 31: 
(In millions, except percentages)
2013

 
2012

Total remediation costs—undiscounted
$
198


$
202

Weighted average risk-free rate
5.6
%

5.6
%
Total remediation costs—discounted
$
133


$
131

Recoverable portion
90


86


 
We also lease certain government-owned properties and generally are not liable for remediation of preexisting environmental contamination at these sites. As a result, we generally do not provide for these costs in our consolidated financial statements.
Due to the complexity of environmental laws and regulations, the varying costs and effectiveness of alternative cleanup methods and technologies, the uncertainty of insurance coverage and the unresolved extent of our responsibility, it is difficult to determine the ultimate outcome of environmental matters; however, we do not expect any additional liability to have a material adverse effect on our financial position, results of operations or liquidity.

Environmental remediation costs expected to be incurred are:
(In millions)
 
2014
$
43

2015
19

2016
15

2017
11

2018
10

Thereafter
100



Financing Arrangements and OtherWe issue guarantees, and banks and surety companies issue, on our behalf, letters of credit and surety bonds to meet various bid, performance, warranty, retention and advance payment obligations of us or our affiliates. These instruments expire on various dates through 2023. Additional guarantees of project performance for which there is no stated value also remain outstanding. The stated values outstanding consisted of the following at December 31: 
(In millions)
2013

 
2012

Guarantees
$
378


$
255

Letters of Credit
1,424


1,474

Surety Bonds
238


239


 
Included in guarantees and letters of credit described above were $233 million and $268 million, respectively, at December 31, 2013, and $108 million and $225 million, respectively, at December 31, 2012, related to our joint venture in TRS. We provide these guarantees and letters of credit to TRS and other affiliates to assist these entities in obtaining financing on more favorable terms, making bids on contracts and performing their contractual obligations. While we expect these entities to satisfy their loans, and meet their project performance and other contractual obligations, their failure to do so may result in a future obligation to us. We periodically evaluate the risk of TRS and other affiliates failing to satisfy their loans, project performance and meet other contractual obligations described above. At December 31, 2013, we believe the risk that TRS and other affiliates will not be able to perform or meet their obligations is minimal for the foreseeable future based on their current financial condition. All obligations were current at December 31, 2013. At December 31, 2013 and December 31, 2012, we had an estimated liability of $8 million and $4 million, respectively, related to these guarantees and letters of credit.

In 1997, we provided a first loss guarantee of $133 million on $1.3 billion of U.S. Export-Import Bank loans (maturing in 2015) to the Brazilian Government related to IDS' System for the Vigilance of the Amazon (SIVAM) program. Loan repayments by the Brazilian Government were current at December 31, 2013.
We have entered into industrial cooperation agreements, sometimes referred to as offset agreements, as a condition to obtaining orders for our products and services from certain customers in foreign countries. At December 31, 2013, the aggregate amount of our offset agreements had an outstanding notional value of approximately $5 billion. These agreements are designed to return economic value to the foreign country by requiring us to engage in activities supporting local defense or commercial industries, promoting a balance of trade, developing in-country technology capabilities, or addressing other local development priorities. Offset agreements may be satisfied through activities that do not require a direct cash payment, including transferring technology, providing manufacturing, training and other consulting support to in-country projects, and the purchase by third parties (e.g., our vendors) of supplies from in-country vendors. These agreements may also be satisfied through our use of cash for activities such as subcontracting with local partners, purchasing supplies from in-country vendors, providing financial support for in-country projects, and making investments in local ventures. Such activities may also vary by country depending upon requirements as dictated by their governments. We typically do not commit to offset agreements until orders for our products or services are definitive. The amounts ultimately applied against our offset agreements are based on negotiations with the customers and typically require cash outlays that represent only a fraction of the notional value in the offset agreements. Offset programs usually extend over several or more years and may provide for penalties in the event we fail to perform in accordance with offset requirements. We have historically not been required to pay any such penalties.

As a government contractor, we are subject to many levels of audit and investigation by the U.S. Government relating to our contract performance and compliance with applicable rules and regulations. Agencies that oversee contract performance include: the Defense Contract Audit Agency, the Defense Contract Management Agency, the Inspector General of the Department of Defense and other departments and agencies, the Government Accountability Office, the Department of Justice and Congressional Committees. From time to time, these and other agencies investigate or conduct audits to determine whether our operations are being conducted in accordance with applicable requirements. Such investigations and audits could result in administrative, civil or criminal liabilities, including repayments, fines or penalties being imposed upon us, the suspension of government export licenses or the suspension or debarment from future U.S. Government contracting. U.S. Government investigations often take years to complete and many result in no adverse action against us. Our final allowable incurred costs for each year are also subject to audit and have from time to time resulted in disputes between us and the U.S. Government with litigation resulting at the Court of Federal Claims (COFC) or the Armed Services Board of Contract Appeals (ASBCA) or their related courts of appeals. In addition, the Department of Justice has, from time to time, convened grand juries to investigate possible irregularities by us. We also provide products and services to customers outside of the U.S. and those sales are subject to local government laws, regulations, and procurement policies and practices. Our compliance with such local government regulations or any applicable U.S. Government regulations (e.g., the Foreign Corrupt Practices Act and the International Traffic in Arms Regulations) may also be investigated or audited. Other than as specifically disclosed herein, we do not expect these audits, investigations or disputes to have a material effect on our financial position, results of operations or liquidity, either individually or in the aggregate.
  
On July 22, 2010, Raytheon Systems Limited (RSL) was notified by the UK Border Agency (UKBA) that it had been terminated for cause on a program. The termination notice included allegations that RSL had failed to perform on certain key milestones and other matters in addition to claiming entitlement to recovery of certain losses incurred and previous payments made to RSL. We believe that RSL performed well and delivered substantial capabilities to the UKBA under the program, which has been operating successfully and providing actionable information since live operations began in May 2009. As a result of the termination notice, we adjusted our estimated amounts of revenue and cost under the program in the second quarter of 2010. On July 29, 2010, RSL filed a dispute notice on the grounds that the termination by the UKBA was not valid. On August 18, 2010, the UKBA initiated arbitration proceedings on this issue. On March 22, 2011, the UKBA gave notice that it had presented a demand to draw on the approximately $80 million of letters of credit provided by RSL upon the signing of the contract with the UKBA in 2007. On March 23, 2011, the UKBA submitted a detailed claim in the arbitration of approximately £350 million (approximately $579 million based on foreign exchange rates as of December 31, 2013) for damages and clawback of previous payments, plus interest and arbitration costs, excluding any credit for capability delivered or draw on the letters of credit. The UKBA also asserted that additional amounts may be detailed in the claim in the future if estimates of its damages change, and for continuing post-termination losses and any re-procurement costs, which have not been quantified. At RSL's request, on March 29, 2011, the Arbitration Tribunal issued an interim order restraining the UKBA from drawing down on the letters of credit pending a hearing on the issue. Following the hearing, the Tribunal lifted the restraint on the basis that, at this early stage of the proceedings, the Tribunal had not heard the evidence needed to decide the merits of whether the contractual conditions for a drawdown had been established. The Tribunal also concluded that any decision on the UKBA's right to call on the letters of credit is inextricably intertwined with the ultimate decision on the merits in the arbitration. The Tribunal also preserved RSL's right to claim damages should RSL later establish that the drawdown was not valid. As a result, on April 6, 2011, the UKBA drew the $80 million on the letters of credit.

As a result of the Tribunal's decision that the letters of credit are inextricably intertwined with the ultimate decision on the merits in the arbitration, we were no longer able to evaluate, independently from the overall claim, the probability of recovery of any amounts drawn on the letters of credit. We therefore recorded $80 million of costs related to the UKBA drawdown (UKBA LOC Adjustment), which was included in the operating expenses of our Intelligence, Information and Services (IIS) segment in the first quarter of 2011.

In June 2011, RSL submitted in the arbitration its defenses to the UKBA claim as well as substantial counterclaims in the amount of approximately £500 million (approximately $827 million based on foreign exchange rates as of December 31, 2013) against the UKBA for the collection of receivables, damages and interest. On October 3, 2011, the UKBA filed its reply to RSL's counterclaims, and increased its claim amount by approximately £32 million, to include additional civil service and post termination costs, and approximately £33 million for interest, raising the gross amount of the UKBA claim for damages and clawback of previous payments to approximately £415 million (approximately $687 million based on foreign exchange rates as of December 31, 2013). On January 6, 2012, RSL filed its response to the UKBA's reply. RSL is pursuing vigorously the collection of all receivables for the program and damages in connection with the wrongful termination and is mounting a strong defense to the UKBA's alleged claims for losses and previous payments. RSL has also settled substantially all subcontractor claims, novated all key subcontracts to the UKBA and agreed with the UKBA that RSL's exit obligations to operate the previously delivered capability ended in April 2011. Effective April 15, 2011, the UKBA took over responsibility for operating the previously delivered capability. In March 2013, the UKBA updated the total net amount of its claims to approximately £302 million (approximately $500 million based on foreign exchange rates as of December 31, 2013) for damages, clawback of previous payments and interest, and inclusive of a credit for capability delivered by RSL. Arbitration hearings commenced in late 2012 and were completed in 2013. We expect a decision in the first half of 2014.

The receivables and other assets remaining under the program for technology and services delivered were approximately $40 million at December 31, 2013 and 2012. We believe the remaining receivables and other assets are probable of recovery in litigation or arbitration. We currently do not believe it is probable that RSL is liable for losses, previous payments (which includes the $80 million related to the drawdown on the letters of credit), clawback or other claims asserted by the UKBA either in its March 2011 arbitration filing or its October 2011 reply. Due to the inherent uncertainties in litigation and arbitration, and the complexity and technical nature of actual and potential claims and counterclaims, it is reasonably possible that the ultimate amount of any resolution of the termination could be less or greater than the amounts we have recorded. For the same reasons, at this time, we are unable to estimate a range of the possible loss or recovery, if any, beyond the claim and counterclaim amounts. If we fail to collect the receivable balances or are required to make payments against claims or other losses asserted by the UKBA in excess of the amounts we have recorded, it could have a material adverse effect on our financial position, results of operations or liquidity.
On June 29, 2012 and July 13, 2012, we received a contracting officer’s final decision (COFD) for 2004 and 2005 incurred costs at SAS. The COFDs demand a total payment of $241 million for costs, interest and penalties associated with several issues, the largest of which relates to specific research and development and capital projects undertaken by SAS between 2000 and 2005. To date, no COFDs have been provided for 2000 to 2003 periods at SAS on these issues. The Government alleges that the costs incurred on the projects should have been charged directly to U.S. Government contracts rather than through indirect rates and that these costs should not be recoverable. We strongly disagree with the Government's position. We have requested a deferment of the payment and in February and May 2013, we filed complaints in the U.S. COFC challenging the 2004 and 2005 COFDs, respectively. Due to the inherent uncertainties of litigation, we cannot estimate a range of potential loss. We believe that we appropriately charged the disputed costs based on government accounting standards and applicable precedent and properly disclosed our approach to the Government. We also believe that in many cases, the statute of limitations has run on the issues. Based upon the foregoing, we do not expect the results of the COFDs to have a material impact on our financial position, results of operations or liquidity.
In addition, various other claims and legal proceedings generally incidental to the normal course of business are pending or threatened against, or initiated by, us. We do not expect any of these proceedings to result in any additional liability or gains that would materially affect our financial position, results of operations or liquidity. In connection with certain of our legal matters, we may be entitled to insurance recovery for qualified legal costs. We do not expect any insurance recovery to have a material impact on the financial exposure that could result from these matters.
As part of the 2013 business consolidation, the total costs of the severance benefits to terminated employees were not material, and almost all of the costs were incurred in accordance with existing termination benefit plans and not as one-time termination benefits. Additionally, relocation and other costs associated with the business consolidation were not material. Although not material, the majority of these costs will be recovered in our overhead rates.

Product Warranty—We provide for product warranties in conjunction with certain product sales for which we recognize revenue upon delivery.

Activity related to product warranty accruals was as follows: 
(In millions)
 
2013

 
2012

 
2011

Beginning balance
 
$
33

 
$
38

 
$
43

Provisions for warranties
 
3

 
5

 
4

Warranty services provided
 
(6
)
 
(10
)
 
(9
)
Ending balance
 
$
30

 
$
33

 
$
38


 
We account for warranty provision costs incurred under our long-term contracts using the cost-to-cost measure of progress as contracts costs, as the estimation of these costs is integral in determining the price of the related long-term contracts. The table above excludes these costs.
 

us-gaap:CommitmentsAndContingenciesDisclosureTextBlock