Pernix Group, Inc. | 2013 | FY | 3


11. Cost and Estimated Earnings on Uncompleted Contracts

 

Long-term construction contracts in progress are accounted for using the percentage-of-completion method.

 Billings, costs incurred, and estimated earnings on uncompleted contracts as of December 31, 2013 and 2012 were as follows:

 

 

 

 

 

 

 

 

Cost and Estimating Earnings on Uncompleted Contracts

 

December 31, 2013

 

 

December 31, 2012

Cost incurred on uncompleted contracts

$

 211,750,908  

 

$

147,874,837 

Estimated earnings

 

 18,207,952 

 

 

14,332,709 

        Total cost and estimated earnings

 

229,958,860 

 

 

162,207,546 

Less: Billings to date

 

                            238,309,368

 

 

171,124,928 

        Net

 

(8,350,508)

 

 

(8,917,382)

 

 

 

 

 

 

 

These amounts are included in the accompanying consolidated balance sheets under the following captions:

 

 

 

 

 

 

Costs and estimated earnings in excess of billings on uncompleted contracts

 

56,679 

 

 

— 

Billings in excess of costs and estimated earnings on uncompleted contracts

 

(8,407,187) 

 

 

(8,917,382) 

 

$

(8,350,508) 

 

$

(8,917,382) 


us-gaap:LongTermContractsOrProgramsDisclosureTextBlock